New Facility Project Reaches Major Milestone

 

20160127_UBC-AC_LuckyLoonies_IMG_7688_CherihanPhotography vs2

January marks a significant milestone for the new UBC Aquatic Centre project as the new facility’s roof is now complete. UBC staff and athletes took time out this week to acknowledge the work of the construction crew, some of whom have been working on-site since the start of the $39-million project in August 2014. The project continues to be on track for completion for late fall 2016. More information on this story is available here
Come together with neighbours and share pool programming ideas with staff at the UBC Athletics & Recreation Open House scheduled for Friday February 19th (3-6pm). More information on this project is available here.